In a report today the House of Commons select committee on energy security and net zero calls on the Government to publish a new “nuclear roadmap”: an updated policy plan for UK nuclear power that sets out evidence-based deployment targets and clear delivery plans for gigawatt-scale reactors, small modular reactors (SMRs) and advanced modular reactors (AMRs).

As part of that, the Committee says Great British Energy-Nuclear must deliver three, not two, completed Final Investment Decisions by the end of this Parliament, to better align delivery with long-term nuclear objectives.

  • Current commitments to achieve 70% of UK content in the SMR development supply chains are not sufficiently enforceable to send the needed signal to encourage investment in domestic supply chains, secure high-value manufacturing jobs and create export opportunities for UK industry.
  • Pathways into the nuclear workforce should be expanded and with clearer accountability for delivery against targets in the National Nuclear Strategic Plan for Skills.
  • Nuclear power regulation must become more proportionate and less burdensome: improving international regulatory cooperation and reforming “outdated” reactor siting rules that hinder deployment of new, advanced technologies.
  • The financing model used for Sizewell C transfers significant construction risk to consumers and should be scrutinised before it is extended to any future projects.
  • Public funding support for first-of-a-kind technologies must be reserved for projects that will lead to deployment at scale and provide value for consumers and taxpayers.
  • Progress on the new Geological Disposal Facility (GDF) essential for future nuclear expansion must be accelerated with a preferred site identified before the end of this Parliament.

The UK’s historic “stop-start” approach to nuclear development has resulted in decades of underinvestment in the nuclear workforce and supply chains. It is argued that a predictable pipeline of reactor orders could encourage investment in domestic supply chains, secure high-value manufacturing jobs and create export opportunities for UK industry.

However, concerns remain that current commitments to achieving 70% UK content in the SMR programme are not sufficiently enforceable. We recommend stronger contractual requirements and greater transparency over how UK supply chain commitments will be measured and monitored. Pathways into the nuclear workforce should be expanded and there must be clearer accountability arrangements for delivery against targets in the National Nuclear Strategic Plan for Skills. To strengthen energy resilience, we also call for a formal assessment of whether the UK should develop a civil nuclear test reactor.

Clare Rhodes-James, Development director – energy, Mott MacDonald, says, “Today’s report gets to the heart of the challenge. What the UK’s nuclear industry needs is a long-term pipeline to provide certainty and confidence. This is the key to unlocking progress in our nuclear infrastructure, and the wider positive knock-on effects this could have on UK growth. Long-term security is the best way to build skills, for instance, and it gives businesses and people the confidence to commit. Developers, investors, regulators, skills providers, and the supply chain are unlikely to sign on at the necessary scale without confidence that there will be a continuing programme. At the same time, to alleviate supply chain constraints and create UK value, select industrial interventions should be deployed. 

“However, with today’s political focus on affordability a guarantee of any ongoing programme will be challenging and will likely become one of the biggest practical constraints on the scale of development. We need to find a financing model which is both investable and politically acceptable, and must remember that moving cost or risk away from consumers does not make it disappear.“